The Beach House Construction Updates Q1 2026
Master Developer Approval
:
100%
Initial Design Approval by Local Authorities
:
100%
Main Works Mobilization
:
100%
Excavation Works
:
100%
Enabling Works Site Mobilization
:
100%
Soil investigation
:
100%
Soil improvement
:
100%
Shoring system
:
100%
Dewatering System
:
Fully installed and operational
Piling works
:
100%
Building Permit
:
Obtained from RAKM
Main Contractor
:
Appointed and commenced main works
Supervision Consultant
:
Appointed for main works and commenced duties
Pile Head Breaking (Raft Foundation)
:
100%
Pile Head Treatment
:
100%
Water proofing for two basements
:
100%
Raft foundation reinforcement
:
100%
Basement 2 Retaining walls and verticals
:
100%
Covering slab of Basement 2 level
:
100%
Basement 1 Retaining wall and verticals
:
100%
Covering slab on Basement 1 level
:
95%
Verticals of Ground floor slab
:
100%
The Beach House
View More
View Less
marzo de 2026








enero de 2026









diciembre de 2025
noviembre de 2025









octubre de 2025




agosto de 2025
junio de 2025









mayo de 2025
abril de 2025














marzo de 2025