The Beach House Construction Updates Q3 2026
Master Developer Approval
:
100%
Initial Design Approval by Local Authorities
:
100%
Casting of Basement 1 floor slab
:
100%
Basement 1 Retaining wall and verticals
:
100%
Enabling Works Site Mobilization
:
100%
Soil investigation
:
100%
Soil improvement
:
100%
Shoring system
:
100%
Dewatering System
:
Fully installed and operational
Piling works
:
100%
Building Permit
:
Obtained from RAKM
Main Contractor
:
Appointed and commenced main works
Supervision Consultant
:
Appointed for main works and commenced duties
Main Works Mobilization
:
100%
Excavation Works
:
100%
Pile Head Breaking (Raft Foundation)
:
100%
Pile Head Treatment
:
100%
Water proofing for two basements
:
100%
Raft foundation reinforcement
:
100%
Basement 2 Retaining walls and verticals
:
100%
Casting of Ground floor slab
:
100%
Verticals of Ground floor
:
100%
Casting of 1st floor slab
:
100%
Vertical of 1st floor
:
100%
Casting of 2nd floor slab
:
100%
Verticals of 2nd floor
:
100%
Casting of 3rd floor slab
:
100%
Verticals of 3rd floor
:
100%
Casting of 4th floor slab
:
100%
Vertical of 4th floor
:
100%
Casting of 5th floor slab
:
60%
Masonry block work done
:
16%
Plastering work done
:
12%
MEP Work Done
:
5%
The Beach House
View More
View Less
August 2026









July 2026











June 2026












May 2026









April 2026


marzo de 2026








enero de 2026









diciembre de 2025
noviembre de 2025









octubre de 2025




agosto de 2025
junio de 2025









mayo de 2025
abril de 2025














marzo de 2025

















.avif)









.png)












.webp)
.webp)
.webp)