The Beach Residences
Project Site Mobilization
:
Completed
Soil Investigation
:
Done
Soil Improvement
:
Completed
Completion of Enabling works
:
Original Scope is Completed / Additional Shoring Works in Progress , 45% Done.
Dewatering System
:
Installation Completed
Excavation
:
Completed 1st Stage up to Pile Platform level, Stage 2 on progress.
Piling works
:
Piling Permit issued from Rak Municipality , Piling Works on progress, 75% Done.
Commencement Date issued to
:
Main Contractor
Main Project Works
:
Building Permit issued from Rak Municipality.
Main Contractor Office Mobilization
:
Completed
Commencement Date issued to
:
Main Contractor
The Beach Residences
View More
View Less
March 2026





January 2026




December 2025
November 2025












.avif)

October 2025




August 2025
July 2025






















.webp)


%20(1).webp)





.png)













.webp)
.webp)
.webp)