The Beach Residences
Project Site Mobilization
:
Completed
Soil Investigation
:
Done
Soil Improvement
:
Completed
Completion of Enabling works
:
Original Scope is Completed / Additional Shoring Works in Progress , 45% Done.
Dewatering System
:
Installation Completed
Excavation
:
Completed 1st Stage up to Pile Platform level, Stage 2 on progress.
Piling works
:
Piling Permit issued from Rak Municipality , Piling Works on progress, 75% Done.
Commencement Date issued to
:
Main Contractor
Main Project Works
:
Building Permit issued from Rak Municipality.
Main Contractor Office Mobilization
:
Completed
Commencement Date issued to
:
Main Contractor
The Beach Residences
View More
View Less
June 2026






May 2026










April 2026

March 2026





January 2026




December 2025
November 2025












.avif)

October 2025




August 2025
July 2025






















.webp)


%20(1).webp)





.png)













.webp)
.webp)
.webp)