The Beach House Construction Updates Q3 2026
Master Developer Approval
:
100%
Initial Design Approval by Local Authorities
:
100%
Casting of Basement 1 floor slab
:
100%
Basement 1 Retaining wall and verticals
:
100%
Enabling Works Site Mobilization
:
100%
Soil investigation
:
100%
Soil improvement
:
100%
Shoring system
:
100%
Dewatering System
:
Fully installed and operational
Piling works
:
100%
Building Permit
:
Obtained from RAKM
Main Contractor
:
Appointed and commenced main works
Supervision Consultant
:
Appointed for main works and commenced duties
Main Works Mobilization
:
100%
Excavation Works
:
100%
Pile Head Breaking (Raft Foundation)
:
100%
Pile Head Treatment
:
100%
Water proofing for two basements
:
100%
Raft foundation reinforcement
:
100%
Basement 2 Retaining walls and verticals
:
100%
Casting of Ground floor slab
:
100%
Verticals of Ground floor
:
100%
Casting of 1st floor slab
:
100%
Vertical of 1st floor
:
100%
Casting of 2nd floor slab
:
100%
Verticals of 2nd floor
:
100%
Casting of 3rd floor slab
:
100%
Verticals of 3rd floor
:
100%
Casting of 4th floor slab
:
100%
Vertical of 4th floor
:
100%
Casting of 5th floor slab
:
60%
Masonry block work done
:
16%
Plastering work done
:
12%
MEP Work Done
:
5%
The Beach House
View More
View Less
August 2026









July 2026











June 2026












May 2026









April 2026


March 2026








January 2026









December 2025
November 2025









October 2025




August 2025
June 2025









May 2025
April 2025














March 2025

















.avif)









.png)












.webp)
.webp)
.webp)