The Beach House Construction Updates Q1 2026
Master Developer Approval
:
100%
Initial Design Approval by Local Authorities
:
100%
Main Works Mobilization
:
100%
Excavation Works
:
100%
Enabling Works Site Mobilization
:
100%
Soil investigation
:
100%
Soil improvement
:
100%
Shoring system
:
100%
Dewatering System
:
Fully installed and operational
Piling works
:
100%
Building Permit
:
Obtained from RAKM
Main Contractor
:
Appointed and commenced main works
Supervision Consultant
:
Appointed for main works and commenced duties
Pile Head Breaking (Raft Foundation)
:
100%
Pile Head Treatment
:
100%
Water proofing for two basements
:
100%
Raft foundation reinforcement
:
100%
Basement 2 Retaining walls and verticals
:
100%
Covering slab of Basement 2 level
:
100%
Basement 1 Retaining wall and verticals
:
100%
Covering slab on Basement 1 level
:
95%
Verticals of Ground floor slab
:
100%
The Beach House
View More
View Less
March 2026








January 2026









December 2025
November 2025









October 2025




August 2025
June 2025









May 2025
April 2025














March 2025