Island Heights Construction Updates Q4 2026
Project Site Mobilization
:
Completed
Piling works
:
Piling Permit issued from RAK Municipality, Piling Works Completed, Piles Tests Ongoing 85% Done.
Tendering of Main works
:
Contract is Signed with the Main Contractor.
Main Project works
:
Building Permit Issued from RAK Municipality.
Soil Improvement
:
Completed
Excavation
:
Completed up to Piling Platform level, and 30% up to Raft Level done.
Enabling works
:
Secant Pile & Caping Beam Completed, Waler Beam & Strut Works Starting.
Soil Investigation
:
Done
Island Heights
View More
View Less