The Beach Residences Construction Updates Q3 2026
Project Site Mobilization
:
Completed
Soil Investigation
:
Done
Soil Improvement
:
Completed
Completion of Enabling works
:
Original Scope is Completed / Additional Shoring Works in Progress, 75% Done.
Dewatering System
:
Installation Completed
Excavation
:
Enabling Package Completed.
Piling works
:
Piling Permit issued from RAK Municipality, Piling Works Completed, Pile Test on Progress 80% Done.
Main Works Status
:
Foundation Works on Progress, 15% Done.
Commencement Date issued to
:
Main Contractor
Tendering of Main works
:
Contract is Signed with the Main Contractor.
Main Project Works
:
Building Permit Issued from Rak Municipality.
Main Contractor Office Mobilization
:
Completed
Commencement Date issued to
:
Main Contractor
The Beach Residences
View More
View Less
August 2026






July 2026






June 2026






May 2026










April 2026

mars 2026





Janvier 2026




Décembre 2025
Novembre 2025












.avif)

Octobre 2025




Août 2025
Juillet 2025






















.webp)


%20(1).webp)





.png)













.webp)
.webp)
.webp)