The Beach House Construction Updates Q1 2026
Master Developer Approval
:
100%
Initial Design Approval by Local Authorities
:
100%
Main Works Mobilization
:
100%
Excavation Works
:
100%
Enabling Works Site Mobilization
:
100%
Soil investigation
:
100%
Soil improvement
:
100%
Shoring system
:
100%
Dewatering System
:
Fully installed and operational
Piling works
:
100%
Building Permit
:
Obtained from RAKM
Main Contractor
:
Appointed and commenced main works
Supervision Consultant
:
Appointed for main works and commenced duties
Pile Head Breaking (Raft Foundation)
:
100%
Pile Head Treatment
:
100%
Water proofing for two basements
:
100%
Raft foundation reinforcement
:
100%
Basement 2 Retaining walls and verticals
:
100%
Covering slab of Basement 2 level
:
100%
Basement 1 Retaining wall and verticals
:
100%
Covering slab on Basement 1 level
:
95%
Verticals of Ground floor slab
:
100%
The Beach House
View More
View Less
mars 2026








Janvier 2026









Décembre 2025
Novembre 2025









Octobre 2025




Août 2025
Juin 2025









Mai 2025
Avril 2025














Mars 2025