Новости строительства пляжного домика за 1 квартал 2026 года
Master Developer Approval
:
100%
Initial Design Approval by Local Authorities
:
100%
Main Works Mobilization
:
100%
Excavation Works
:
100%
Enabling Works Site Mobilization
:
100%
Soil investigation
:
100%
Soil improvement
:
100%
Shoring system
:
100%
Dewatering System
:
Fully installed and operational
Piling works
:
100%
Building Permit
:
Obtained from RAKM
Main Contractor
:
Appointed and commenced main works
Supervision Consultant
:
Appointed for main works and commenced duties
Pile Head Breaking (Raft Foundation)
:
100%
Pile Head Treatment
:
100%
Water proofing for two basements
:
100%
Raft foundation reinforcement
:
100%
Basement 2 Retaining walls and verticals
:
100%
Covering slab of Basement 2 level
:
100%
Basement 1 Retaining wall and verticals
:
100%
Covering slab on Basement 1 level
:
95%
Verticals of Ground floor slab
:
100%
The Beach House
View More
View Less
Март 2026








Январь 2026 года









Декабрь 2025 года
Ноябрь 2025 года









Октябрь 2025 года




Август 2025
Июнь 2025 года









Май 2025 года
April 2025














Март 2025 года

















.avif)









.png)












.webp)
.webp)
.webp)